PROJECT OVERVIEW
Record-Breaking Completion of a 1,000,000 sq. ft. Facility
1,000,000 square foot “Just In Time” delivery facility located in Stanton Tennessee is part of the Ford Blue Oval project. Gen-Co was involved heavily in design assist and completed the job in a record time of ten months.
Gen-Co’s workforce and years of electrical experience were instrumental in keeping pace with this rigorous schedule by working six days a week in order to complete the job on time and within budget.